Sun Photos by Phil Gentry
In the photo above, Travis Brickey, left, a spokesman for the Tennessee Department of Transportation, explains short-term closings of I-81. A temporary brace is behind him. To his left is Randy Seger, head of TDOT's bridge inspection office. At right in the foreground is Paul Degges, TDOT chief engineer. The photo below, at left, reveals a small crack, about three to four inches long, in one beam. The photo below, at right, shows the beams that support the bridge.
Beginning this
Saturday night at 10 p.m., northbound traffic on Interstate 81 will have to take Exit 23 at Mosheim,
cross U.S. Highway 11E, and take the on-ramp to continue
northward.
Enlarged crews from General Constructors, of Mt. Juliet,
Tenn., will be working through the night of Nov. 14-15 to repair two small "metal fatigue cracks" in
the beams underneath the interstate bridge, said Paul Degges, chief engineer with the Tennessee
Department of Transportation.
By 10 a.m. on Sunday, normal northbound
traffic is expected to be restored on Interstate 81, Degges said. "We hope to get done faster than
this," he said.
Traffic must be diverted from the bridge because
vibrations from traffic passing overhead would make it impossible to properly perform repairs
involving welding, Degges said.
A week later, on the night of Nov. 20,
southbound traffic will have the same diversion, again while crews work through the night to repair
a single crack in one beam under the southbound bridge, Degges said.
Each
of the bridges is supported by five beams, Degges said, so even if one beam were to fail, the
"redundant" beams would be expected to support the bridge.
Deggs and
others said TDOT scheduled a press conference underneath the bridge on Tuesday to emphasize the
agency's belief that there is no danger of the bridge failing.
TRAFFIC TO BE DIRECTED
In both 12-hour repair periods, law
enforcement officers will be on hand to direct traffic, and every effort will be made to alert
motorists ahead of time.
"Traffic will still be able to flow," Degges
said. Motorists will be able to travel in both directions on 11E and on I-81, and will be able to
use all on-ramps and off-ramps.
However, he said, because of the
difficulty of routing traffic from one off-ramp to the opposite on-ramp, priority will be given to
traffic on Interstate 81.
Degges added that anyone traveling through the
interchange on U.S. 11E at Exit 23 should expect delays during the 12-hour period each
weekend.
Julie Oaks, a TDOT public information officer, and Travis
Brickey, a TDOT spokesperson, said law enforcement from Greene County and the Tennessee Highway
Patrol will be present at the bridge and in the vicinity while the repairs are being
made.
Obviously, priority will have to be given to traffic on the
interstate highway while the repairs are being made, Oaks and Brickey
said.
Persons who normally use either I-81 or U.S. Highway 11E to travel
to church on Sunday will need to either consider an alternate route or plan to be delayed, Brickey
said.
Greene County Sheriff Steve Burns said TDOT asked him to make three
cruisers available to help direct traffic, and he plans to do so.
INTERSTATE 40 DETOUR
Alerting motorists will be complicated
somewhat by the fact that many who will be traveling the highway will already have been diverted
onto I-81 due to a rock slide that has closed Interstate 40 just east of the North Carolina line,
said TDOT's Brickey.
The I-40 detour will not be altered during the
repairs.
Degges said the fact that I-81 is already carrying extra traffic
is "unfortunate," but was not a big enough factor, by itself, to postpone the
repairs.
Degges said the contractor had been rehabilitating the beams as
part of a $1.2 million project that includes bridge deck repairs, painting and installation of a
system to detect trucks that are too high to pass under the bridge and stop them before they damage
it.
CRACKS IDENTIFIED
In the process,
the contractor identified two cracks in beams under the northbound bridge, and one under the
southbound bridge.
"TDOT believes the cracks developed some time after
the last bridge inspection was conducted in July 2008," according to a press
release.
It is estimated the cost of the additional repairs will be
$79,271.
Crews will use a welding technique called "full penetration
welding," in which molten metal is created during the process. The molten metal "penetrates the
entire bridge beam" and eliminates the cracks.
Before traffic is allowed
to resume crossing the bridge, the weld will be x-rayed to make sure it was performed correctly,
Degges said.
ADDITIONAL TESTING
Wayne
Seger, manager of TDOT's bridge inspection and repair office, said additional testing was to begin
today.
He said the repair to the southbound bridge would involve
removing a section smaller than one square foot from the vertical "web" of the beam, and welding a
steel plate back to replace it. Degges said the bridges at Exit 23 were built in
1968.
Bridges normally have "about a 50-year life expectancy, but it's
not unusual to get 100 years of service out of a bridge." He noted that several bridges in Knoxville
are 100 years old.
Federal law calls for bridge inspections on a 24-month
cycle, he said.
Rehabilitation work, such as the work in which the
"metal fatigue cracks" were discovered, are part of an ongoing effort to extend bridge life, Degges
said.
Additional Photos (click thumbnail
to enlarge)
For more information and stories, see today's edition of The Greeneville Sun.
Subscribe to The Greeneville Sun by clicking SUBSCRIBE.
Sign up for Breaking News emails from the Sun by clicking EMAIL ALERTS and inputting
your email address next to "Add Me" near the top right corner.