Built By Contractor Now Working On I-40 In
Knoxville
By TOM YANCEY
Staff
Writer
A new, wider, safer bridge over Lick Creek on North Mohawk
Road was officially opened Friday with a ribbon-cutting by county and state elected
officials.
County Road Superintendent David Weems said work on the
project was authorized in mid-August of 2007 and was completed in mid-March of this
year.
Tim Teague, the project engineer with W&W Engineering, of
Greeneville, said actual construction by the general contractor, Charles Blalock & Sons, Inc.,
of Sevierville, began Sept. 24.
Teague said the new bridge is wider and
considerably stronger than the bridge it replaced.
The bridge has parapet
railing 42 inches tall on each side.
The old bridge had only about 19
feet of inside width, said project foreman Jimmy Weeks, while the new one features 24 feet, 6 inches
of "travelable" width.
Teague said the original bid from Blalock was
$509,750, but may be revised when the final paperwork is submitted.
Blalock & Sons was the general contractor on the Oscar B. Lovette
Bridge on the Asheville Highway in 2006, and currently is the contractor on the massive "Smart Fix
40" interstate project in Knoxville.
Weems said Blalock & Sons was
"very cooperative and easy to work with, and they did a good job."
County
Mayor Alan Broyles said, "The county appreciates this cooperative effort of the county Highway
Department and the state. It's another example of how people working together make good things
happen."
State Covers 80 Percent
Because the Lick Creek bridge replacement was a "state aid" project, 80 percent of
the cost will be covered by the Tennessee Department of Transportation, and 20 percent by Greene
County's government.
Road Superintendent Weems said the county Highway
Department constructed the bridge approaches and paved them after the bridge was done, and also
installed guard rails. The county Highway Department also provided fill dirt. He said the roadway
will be paint-striped to complete the county's work.
Weems said he thinks
that the county has performed enough of this "in-kind" work to meet the 20 percent cost-share
requirement. Teague agreed.
Weems said he hopes to be able to replace
another bridge in the county next year as a state-aid project, if funds are
available.
State Rep. Eddie Yokley, R-11th, of Greene County, said he was
pleased that the state "has been able to fund bridges, as we're doing. Hopefully, we'll continue to
see our district continuously improved with new bridges, since Greene County has so many" that need
upgrading, "literally in the hundreds," Yokley said.
State Rep. David
Hawk, R-1st, of Greeneville, said he was also "pleased to be able to support this project in Greene
County."
Traffic that would normally have used the bridge to travel from
Mohawk Crossroads on U.S. Highway 11E to the community of Mohawk has been detoured since last fall
to Idell Road, Porter Kite Road and Phillipi Road.
Weems and County Mayor
Alan Broyles thanked the citizens of Mohawk and the surrounding area for their patience while the
bridge was being built.
Improved Water Line
Teague, the project engineer, said the Old Knox Utility District had a water line
suspended under the old bridge, but the utility has decided to bore through rock under the creek and
install a new high-density polyethylene pipe as a replacement for the old
line.
The old line was four inches in diameter, he said, but the utility
district decided to replace it with an eight-inch line, which should improve water flow in the
Mohawk area once that work is completed.
Teague said the utility district
has routed water to the Mohawk area by several other water lines during construction, and that work
should be completed soon.